Saturday, January 27, 2007
WORK SHEET
xmlns="http://www.w3.org/TR/REC-html40">
style='font-size:18.0pt'>MALVERN PROJECT: ENTIRE JOB LIST
KEY:
Ian BOLD
Johanna Plain text
Chantelle Underline
FOYER
Repair ceiling | Cut out loose parts, seal cracks, replaster. |
Repair Front Door Weatherstripping. | |
Strip Wallpaper | |
Repair Walls | |
Paint ceiling | |
Hang Beige damask wallpaper | |
Install carpet runner. | |
Replace missing interior windows | If Chantelle finds some from a salvage yard. |
Hang Light fixtures, mirror | |
MAIN FLOOR HALLWAY
Repair Ceiling. Repair major bulge in hallway. | |
Paint ceiling | |
Strip paper, repair walls. | Some sections might need replacement pending wallpaper |
Paint beige tone to match front entryway wallpaper. | |
| |
| |
| |
KITCHEN
Stove Exhaust Fan Installation | |
Run coax/cable television | |
Replace taps. Level Fridge. | |
Paint out wood on cupboards | |
Install garbage disposal/ | |
Repair walls, trim, window | |
Paint kitchen: Theme Florit | |
Install “tin” backsplash. | |
OFFICE (ENTRY TO BACK DECK)
Strip Wallpaper, sand sills and trim. | |
Install new flooring: reclaimed wood barnboard | |
Change Lighting/electrical: | Install conduit over existing switch wiring and move |
Paint trim, door and window sills BLACK. Ceiling White. | |
Hang Black and White damask wallpaper. | |
Repair/replace doorknob and door mechanism. | |
| |
| |
LIVINGROOM (Larger main room with bay windows)
Repair Ceiling | I am NOT installing faux tin (can’t find style I like) so |
Replace missing baseboard. | |
Strip wallpaper Repair walls Repair trim. | Windows and closet doors will remain wood. |
Closet: Repair plaster – Move television cable | Run coax cable to upstairs bedroom (NOT master bedroom but |
Paint ceiling. | |
Paint non-feature walls | Darker Purple from wallpaper. |
Hang paper on Main wall | Damask Purple on purple. |
Crown Molding. | |
DINING ROOM (South of Living Room, smaller room)
Repair walls, trim. | |
Paint ceiling white. | |
Install crown molding. | |
Paint walls medium purple-based Blue. | Blue (match Upper hall wallpaper, upper hall plaster |
Paint trim and closet with dividers white. (same as ceilings) | |
Bathroom
Install Broan exhaust fan. | In wall? |
Install window. Create wooden sill. | Use reclaimed barnboard flooring leftovers? Purpose: make |
Install clover-pattern sheet metal | Use gold tone, to replace? Vanity doors and allow heat |
Install bottoms inside vanity cabinets. | |
Repair vanity cabinet trim. | |
PAINT | Walls: pale blue, ceiling and shelf interiors Stencils? Behr Blue: Coastal Mist? |
FIX SHOWER TEMPERATURE CONTROL | |
WATER CLOSET (room with toilet)
Install window | |
Repair/create sill? | |
Install new toilet. | Victorian style. |
Paint | Bathroom beige/blue Gold ceiling. Leave wallpaper as is. |
| |
| |
| |
UPSTAIRS HALLWAY
Repair/repaint ceiling on second landing. | Use ceiling white from mainfloor. REMOVE/dispose of |
SPECIAL | By Johanna! Repair paper/ holes/ bulges. Use blue plaster |
Remove, fix, reinstalls railing. | |
Remove carpet from stairs. | |
Repair/clean up stairs and sand stairs for painting. | |
Paint stairs. | Slate blue grey (historic colour Battleship grey from |
| |
| |
Guest Bedroom/ Treadmill room.
Install Coax/television cable. (west end of north | |
Strip wallpaper from back wall | Leave floral wallpaper on walls around closet. |
Repair walls/ceiling. | |
Paint stripped walls/ceiling Yellow | Butter yellow, pale colour. |
| |
MASTER BEDROOM (large center window at front/east side of
house.)
Strip wallpaper border. Repair walls/ceiling. | |
REPLACE ENTIRE WINDOW AND SILL/TRIM. | Waiting on Jeld-wen wood window to arrive. |
Doors remain wood. | |
Paint room Blue | Behr Wave Crest 540E-1 or close to it. (still deciding) |
Paint trim white | Behr 1812 Swiss Coffee W-B-700 |
STAIN new window And trim around | Non-yellow natural stain…”diamond” stain or other. |
| |
| |
| |
NON ROOM-SPECIFIC GENERAL NOTES
Radiators CLEAN-UP | Radiators cleaned, sanded and painted where needed. ESPECIALLY CAPPED RADS: Dining Room Guest Room |
Radiators COVERS: | Painted according to room and installed with sheet-metal FULL COVERS: Foyer top landing Living room Kitchen Office Master Bedroom (bench) |
Light Fixtures | Replaced in each room with new fixtures. |
Move FURNACE | Replace thermostat with programmable digital and move it |
COAX/Television Cable Phone Cable | -run to Living Room and Kitchen and Guest Room from living REMOVED TOTALLY |
SCHEDULE AND FURTHER NOTES.
Roughly each room is in some order of tasks from Ceiling to
floor.
Co-ordination will have to be day-to-day depending what gets
done.
I did a best guest for who will do what but all of that is
of course worked out as we go along.
I will provide you with a set of keys Monday morning
(January 29).
I will be on hand to help with that and we should all
exchange cell-phone numbers on Monday so we can keep updating the schedule.
I will move in Mattress and box springs before upper hall
gets completed because it is a difficult fit.
CHANTELLE’S AVAILABILITY:
January 29- February 2
Morning Afternoon
M | 9 am Pick Johanna up to get supplies. | At Malvern afternoon. |
T | Available on cellphone. | At Malvern afternoon. |
W | Available on cellphone. | At Malvern afternoon. |
Th | 9 am at Malvern. | At Malvern afternoon. |
F | 9 am at Malvern. | Leaving at 2pm. |
February 5 - 9
Morning Afternoon
M | 9 am at Malvern. | At Malvern afternoon. |
T | 9 am at Malvern. | At Malvern afternoon. |
W | 9 am at Malvern. | At Malvern afternoon. |
Th | 9 am at Malvern. | At Malvern afternoon. |
F | 9 am at Malvern. | At Malvern afternoon. |